What is the minimum curing period?

What is the minimum curing period? What is the minimum curing period?
For most concrete structures, the curing period at temperatures above 5º C should be a minimum of 7 days or until 70% of the specified compressive or flexural strength is attained. The period could be reduced to 3 days if high early strength concrete is used and the temperature is above 10º C.

Reference:
What is the minimum curing time for cement concrete? - Quora
Jul 4, 2019

What is the minimum curing period?,frequently asked question,question and answer,answer,